TheEnergyMag
TheEnergyMag|6月 25, 2026 11:57
JUST IN: @HIVEDigitalTech is pairing the 32MW Swedish #AI data center plan with a proposed new $100M financing. Key points: • Non-binding LOI for up to 10-year lease at Boden, Sweden site • 32 MW gross utility load, about 25 MW critical IT load • Planned retrofit for up to 10,000 Nvidia GB300 GPUs • Rack density up to 150 kW with hybrid liquid + air cooling • Proposed $100M 0% exchangeable senior notes due 2031 • Initial purchasers may buy up to an additional $15M • Proceeds earmarked for GPU purchases, data center development and general corporate purposes The plan would repurpose HIVE.N’s legacy GPU mining site in Sweden into an AI/HPC colocation facility.(TheEnergyMag)
+6
Mentioned
Share To

Timeline

HotFlash

APP

X

Telegram

Facebook

Reddit

CopyLink

Hot Reads