*Walter Bloomberg|Dec 12, 2025 16:15
ORACLE PUSHES OPENAI DATA CENTER COMPLETION TO 2028
Oracle has delayed several OpenAI-related data centers from 2027 to 2028 due to labor and material shortages, according to sources. The facilities are part of a $300 billion agreement to supply computing power to OpenAI. While both companies declined to comment, Oracle Co-CEO Clay Magouyrk said timelines remain ambitious, noting the first OpenAI data center in Abilene, Texas, is progressing as planned, with over 96,000 Nvidia chips delivered.(*Walter Bloomberg)