[PJM Proposes to Shorten Data Center Connectivity Study Period to 12 Months] According to a Bloomberg report on November 18th, PJM, a US grid operator, has proposed a "fast-track" plan to shorten the study period required to connect data centers to its grid in 13 states from 24 months to 12 months. This plan will review proposed power plant and transmission facility upgrade projects in parallel. PJM has submitted a proposal to the Federal Energy Regulatory Commission to address the pressure of increasing electricity demand and grid connectivity progress.